MiG-23 Work Resumes

Work has resumed on the Cold War Air Museum's MiG-23UB.

As readers of this blog may know, the Flogger developed a mysterious fuel system leak after ground test in the spring. Replacement parts have now arrived allowing us to resume.

Here are a few photos of the inspection work:

With some clever modification a MiG-23 engine dolly can be made to work as a MiG-23 tail dolly. We were able to pull the tail back to expose inner connections of the single-point fuel port. Interestingly, a US/NATO single-point connection fits perfectly on the Soviet aircraft.


Initially we put 25 liters of fuel into the single-point connection and got 20 liters on the floor. With some fixing, we put 125 liters in and got only 0.5 liters to leak out. Hopefully with some new o-rings the leak will be completely fixed.

The museum's goal is to have the MiG-23 ready for more ground testing, including a test of the afterburner, some time this month.

1 comment:

  1. I am impressed. I don't think Ive met anyone who knows as much about this subject as you do. You are truly well informed and very intelligent. You wrote something that people could understand and made the subject intriguing for everyone. Really, great blog you have got here. core-functional resume format